Sa'gya 300 MW power station enters final debugging process-Xinhua

Sa'gya 300 MW power station enters final debugging process

新华网

Editor: huaxia

2024-10-19 21:43:25

This photo shows wind turbines in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

This photo shows wind turbines in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

This photo shows wind turbines in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

An aerial drone photo shows the Sa'gya 300 MW power station in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

Staff workers examine 35 kV switchgear in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

Staff workers examine power storage facilities in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

Staff members work in the control room of the Sa'gya 300 MW power station in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

Staff workers look at a wind turbine in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

This photo shows animals and a wind turbine in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)

An aerial drone photo shows wind turbines in Sa'gya County of Xigaze City, southwest China's Xizang Autonomous Region, Oct. 17, 2024. The Sa'gya 300 MW power station integrating wind power, solar power and power storage, has entered the final debugging process and is expected to be connected to the grid by the end of this month.

The total installed capacity of the project is 300 MW, of which the total installed capacity of wind power is 200 MW and the total installed capacity of photovoltaic power is 100 MW. It has also built a power storage system and a 62-kilometer external transmission line across the Yarlung Zangbo River. The annual power generation of the project is expected to be close to 550 million kWh after completion. (Xinhua/Jigme Dorje)